Party wall knowledge
Frequently asked questions.
Plain-English answers based on the Party Wall etc. Act 1996 and official government guidance.
Expert guidance
Answers before your project begins.
This information is general guidance, not a definitive interpretation of the law. Project-specific advice depends on the property, ownership and proposed works.
01Do I always need a Party Wall Notice for an extension?
Not always. It depends on whether the work falls within the Act—for example work to a party structure, a new wall at the line of junction, or excavation within the relevant distance and depth. Planning approval alone does not answer this question.
02How much notice must a building owner give?
The usual minimum is two months for work to an existing party structure under section 2, and one month for line-of-junction or qualifying excavation notices under sections 1 and 6. Work may start earlier only where the adjoining owner agrees in writing.
03What happens if an adjoining owner does not reply?
For section 2 or section 6 notices, no written response within 14 days means a dispute is deemed to have arisen. The statutory surveyor appointment procedure can then begin. Section 1 has a different consequence for a proposed wall astride the boundary.
04Can one surveyor act for both owners?
Yes. Both owners may concur in appointing one impartial Agreed Surveyor. Alternatively, each owner appoints a surveyor and those two surveyors select a Third Surveyor.
05Can I act as my own party wall surveyor?
No. An owner who is party to the dispute cannot act as the appointed surveyor under the Act. A suitably experienced independent person should be appointed.
06What is a Party Wall Award?
It is the written determination made by the appointed surveyor or surveyors. It commonly records the works, manner and timing, protective measures, access, the schedule of condition and responsibility for fees.
07Is a Schedule of Condition legally required?
The Act does not expressly require one, but it is usually prudent. A written and photographic record helps distinguish pre-existing defects from damage that may arise during the notified works.
08Who normally pays the surveyors’ fees?
The building owner usually pays reasonable costs arising from works carried out solely for their benefit. Cost responsibility can differ where work benefits both parties or where conduct creates additional expense; the surveyors determine this under the Act.
09Can an adjoining owner stop the work?
An adjoining owner cannot use the Act simply to prevent lawful notified work. They can consent or dissent, and surveyors can regulate how and when work proceeds. If required notice was not served, an adjoining owner may seek legal remedies such as an injunction.
10Does a Party Wall Award settle a boundary dispute?
Generally no. The Act is not a general mechanism for deciding ownership of land or resolving every boundary dispute. Separate legal or specialist boundary advice may be required.
Primary reference: UK Government explanatory booklet.
Start with a conversation
Not sure whether the Act applies?
Tell us about your project and we’ll explain the next step clearly, without obligation.
Book a free consultation
Trinity Party Wall Surveyors